A proposed $19.2 billion artificial-intelligence data center at the Kingsboro Business Park in Edgecombe County, North Carolina, is no longer moving forward at that site. Developer Energy Storage Solutions withdrew its offer to buy more than 100 acres of county-owned industrial land in early July 2026, county officials and multiple local reports confirmed.
The distinction matters: social-media posts have described a roughly $20 billion project as “scrapped,” but the verified development is narrower and more precise. The company withdrew the Kingsboro land-purchase proposal. This report does not claim that every separate data-center plan associated with the developer elsewhere in the Tarboro area has ended.
What was proposed at Kingsboro
Reporting on the proposal described a multi-phase AI computing campus with an estimated investment of $19.2 billion. Published figures varied as plans evolved, but accounts cited an initial capacity of about 300 megawatts and a possible buildout as large as 900 megawatts.

The proposed location was the Kingsboro development area near Tarboro, about 70 miles east of Raleigh. North Carolina Health News reported that residents had opposed the potential sale of 122 acres of county-owned land. A local environmental organization, Sound Rivers, later reported that the developer withdrew an offer covering more than 100 acres.
Those numbers are not necessarily contradictory: one describes the acreage discussed by opponents, while the other describes the withdrawal in the land offer as reported after the decision.
Residents raised infrastructure and environmental concerns
The withdrawal followed months of public meetings and organizing. Residents questioned how a campus of this scale could affect electricity demand, water supplies, utility costs, noise, air quality and nearby communities. Supporters of data-center development also pointed to the potential for investment and tax revenue, creating a difficult trade-off for a rural county seeking economic growth.
Edgecombe County created a Data Center Advisory Group that included a county commissioner, residents with differing views, county staff and subject-matter specialists. The county says the group was designed to examine the effects of growing data-center interest and give balanced policy recommendations to commissioners.

Sound Rivers credited sustained community participation with bringing greater scrutiny to the proposal. Its July 9 report said the developer was no longer considering Kingsboro for the project. Data Center Dynamics independently reported on July 15 that Energy Storage Solutions had withdrawn the proposal, citing comments made by County Manager Eric Evans at the July 6 Board of Commissioners meeting.
What happens next
At the time of the withdrawal, county officials were considering a 24-month moratorium on new data-center development while they studied possible safeguards. The moratorium discussion was separate from the developer’s decision to withdraw the Kingsboro offer, so it should not be described as the legal mechanism that canceled the project.
The episode illustrates a broader debate playing out across rural North Carolina and elsewhere in the United States. Large AI data centers can promise major capital investment, but they can also require extraordinary amounts of electricity and substantial supporting infrastructure. Communities increasingly want clear, enforceable answers about who pays for grid upgrades, how water demand will be managed, what noise limits will apply and how tax incentives compare with long-term local costs.
For Edgecombe County residents, the immediate outcome is clear: the $19.2 billion proposal tied to the Kingsboro county land offer was withdrawn in July 2026. The larger policy debate over data centers in the county remains active.